A. Mandatory Requirement in the Acceptance of Application
01 |
Application Form (MGB Form No. 11-02) |
||
02 |
SEC-certified Certificate of Registration, Articles of Incorporation |
||
03 |
Location Map/Sketch Plan (1:50,000 NAMRIA topographic map) of the area of the proposed processing plant |
||
04 |
Feasibility Study including work programs, plant site, mill and plant layout/design, details of technology to be employed in the proposed operation, anti-pollution devices/measures as well as the plant capacity |
||
05 |
Certificate of Environmental Management and Community Relations Record (CEMCRR) or Certificate of Exemption (COE) |
||
06 |
Environmental Compliance Certificate (ECC) |
||
07 |
Environmental Protection and Enhancement Program (MGB Form 16-2) |
||
08 |
Social Development and Management Program |
||
09 |
Proof of technical competence in the form of: |
||
- |
Bio-data and track records in mining operations/ environmental management |
||
- |
Sworn statement or employment contract/proof of availed service of the technical person/s who will undertake the implementation of the Work Programs |
||
10 |
Interim Importation Permit/certification from EMB on the use of chemicals (e.g. cyanide, mercury) in compliance with R.A. No. 6969 |
||
11 |
Brief history of applicant’s activities for the last five (5) years, if any |
||
12 |
Supply Contract/Agreement with mining rights holders, if applicable |
||
13 |
Proof of financial capability: |
||
- |
Latest audited Financial Statements |
||
- |
Annual Report for the preceding year |
||
- |
Credit Lines/Bank Guarantees/Deposits |
||
14 |
Proof/s of payment of application fee |
||
- |
Project cost of > PhP500M = PhP50,000.00 |
||
- |
Project cost of PhP200-500M = PhP20,000.00 |
||
- |
Project cost of < PhP200M = PhP10,000.00 |
B. Additional Requirements after Acceptance of Application
01 |
MGB reg. Secretary’s Certificate attesting to a Board Resolution authorizing the President to sign and execute documents in connection with the MPP application |
|
02 |
NCIP Certification Precondition |
|
03 |
Proof/s of payment of FS Evaluation Fee = PhP20,000 |
|
04 |
Prior approval or endorsement in the form of Resolution or Certification by at least the majority of the Sanggunian concerned |